VITOGAS 050
Installation and
Service Instructions
Vitogas 050
ECV Series
Natural gas-/Propane-fired
atmospheric cast iron boiler
Rated input: 65 to 200 MBH
19 to 59 kW
Read and save t hese instructions
for f ut ure reference.
IMPORTANT
If the information in this manual is not followed
exactly, a fire or explosion may result causing
property damage, personal injury or loss of life.
WARNING
Do not store or use gasoline or other flammable
liquids in the vicinity of this or any other appliance.
WHAT TO DO IF YOU SMELL GAS
JDo not try to light any appliances.
JDo not touch any electrical switches, do not
use any phone in your building.
JImmediately call your gas supplier from a
neighbor’s phone. Follow the gas supplier’s
instructions.
JIf you cannot reach your gas supplier, call the
fire department.
Installation and service must be performed by a
qualified installer, service agency or the gas
supplier.
Improper installation, adjustment, and/or operation
could cause carbon monoxide poisoning resulting in
injury or loss of life.
This product must be installed and serviced by a
professional service technician who is experienced
and qualified in hot water boiler installation and gas
combustion.
WARNING
5167 450 v1.4 07/2006
Please file in Service Binder
Vedere la pagina 0
1 2 3 4 5 6 ... 51 52

Sommario

Pagina 1 - Service Instructions

VITOGAS 050Installation andService InstructionsVitogas 050ECV SeriesNatural gas-/Propane-firedatmospheric cast iron boilerRated input: 65 to 200 MBH19

Pagina 2

Set-up10Mechanical RoomDuring the early stages of new home design, we recommend that properconsideration be given to constructing a separate mechanica

Pagina 3 - J Hazardous materials

Set-up11Before Set-upDo not use fan blower termination orboiler enclosure paneling to lift/moveboiler into its installation location.The boiler is shi

Pagina 4 - General Information

Set-up12Combustion Air SupplyThis boiler needs fresh air for safeoperation and must be installed so thereare provisions for adequate combustionand ven

Pagina 5 - Initial Start-up and Service

Set-up13Combustion Air Supply (continued)If boiler is installed in a confined space(a space with a volume of less than 50cubic feet per 1000 Btu/h of

Pagina 6 - 5167 450 v1.4

Set-up14Minimum ClearancesRecommended minimum service clearancesSidemm inchesRear: 610 24Top: 610 24Right side: 610 24Left side: 610 24Front: 1220 48A

Pagina 7

Set-up15Minimum Clearances (continued)Closet and alcove installationVitogas 050, ECV-65 to 155 boilers areapproved for closet installation.Vitogas 050

Pagina 8

Set-up16Flushing of Existing PipingLegendReturnSupplyGas pipeAir vent (field supplied)Circulating pumpPressure relief valveCity waterDiaphragm expansi

Pagina 9 - Product Information

Set-up17Removal of Existing BoilerWhen an existing boiler is removed froma common v enting system, the commonventing is likely t o be too large forpro

Pagina 10 - Standard Equipment

Connections18Venting ConnectionThe Vitogas 050, ECV boiler must belocated so that the v ent length is asshort and direct as possible. Theminimum equiv

Pagina 11 - Before Set-up

Connections19Venting Connection (continued)Maximum vent lengthMaximum equivalent v ent length (allmodels) is 20 ft. for 3” of pipe.Maximum equivalent

Pagina 12 - Combustion Air Supply

Safety, Installation and Warranty Requirements2Safety, Installation and Warranty RequirementsPlease ensure that these instructions are read and unders

Pagina 13

Connections20Venting Connection (continued)Installing Z-FLEX pipe and fittingsJ Use liberal beads of silicone to sealjoints.J Use pipe hangers or meta

Pagina 14 - Minimum Clearances

Connections21Venting Connection (continued)Vent terminal connectionThe vent must be installed observinglocal regulations in addition to NationalCodes,

Pagina 15

Connections22Venting Connection (continued)Riser boxIf unable to f ind sufficient clearanceabove grade at the point where the ventpasses through the o

Pagina 16 - Flushing of Existing Piping

Connections23Installation ChecklistPrior to and after the installation, use the following check list to ensure proper installation. Improper installat

Pagina 17 - Removal of Existing Boiler

Connections24Low Water Cut-offIf the ECV boiler is installed aboveradiation level, a low water cut-offdevice must be installed. See Figs. 9and 10 f or

Pagina 18 - Venting Connection

Connections25Initial System FillTreatment for boiler feed water shouldbe considered in areas of knownproblems, such as high mineral contentand hardnes

Pagina 19 - IMPORTANT

Connections26Gas PipingBefore connecting gas boiler to gas line,install main gas shut-off valve, union,and capped drip leg (see Fig. 11 below).Size ga

Pagina 20

Connections27Gas Pressure - Orifice SizesPILOT PRESSURE FOR Q3451A PILOTNatural Gas 5-7”w.c.Propane Gas 8-10”w.c.Natural GasMinimum gas valveinlet pre

Pagina 21

Connections28Gas Burner RemovalLegendSocket wrench (13 mm)Pilot burner location forECV-65, 80, 100, 115, 140, 155Flame roll-out switchManifold pressur

Pagina 22

Connections29Gas Input\1. Close main gas shut-off valv e.2. Disconnect main power supply toboiler.3. Remove plug1/8“ NPT on manifold.Install test plug

Pagina 23 - Installation Checklist

Safety, Installation and Warranty Requirements3Safety, Installation and Warranty Requirements (continued)Please ensure that this manual is read and un

Pagina 24 - Low Water Cut-off

Connections30Main BurnerProper flame: Upper main flame conewith light orange coloring,sharply defined individualflames. See Fig. 13 onprevious page.Un

Pagina 25 - Pressure Relief Valve

Connections31Gas Burner Positioningg (continued)Every ECV boiler will have a flameroll-outswitch(setat200°F/93°C)located in the burner area (see Fig.1

Pagina 26 - Testing Gas Pipe

32Electrical ConnectionsRefer t o wiring diagrams on pages 46and 47. All wiring must be properlygrounded! Before attempting to wireunit, disconnect po

Pagina 27 - Gas Pressure - Orifice Sizes

Connections33Electrical Connections (continued)Pumps under 4 Amp. can be connecteddirectly to boiler terminal strip. Pumpsover 4 Amp. must be switched

Pagina 28 - Gas Burner Removal

Initial Sta rt-up34Initial Start-upThe boiler, piping and radiation must befull of water and purged of all air beforeboiler can be fired. Pressure rel

Pagina 29 - Gas Input

Initial Sta rt-up and Service35Initial Start-upAnnual shut-downIf boiler is used for comfort heating onlyand not used with an indirect-fireddomestic h

Pagina 30 - Gas Burner Positioningg

Initial Sta rt-up and Service36Service ScheduleFrequently - by ownerCheck pressure gage for correct system (water) pres sure.Check for water on floor

Pagina 31

Initial Sta rt-up and Service37Service P rocedure OverviewService stepsS1. Shut down heating system Page 38...

Pagina 32 - Electrical Connections

Initial Sta rt-up and Service38Service Procedure1. Shut down heating systemServiceService1. Deactivate main power and ensureagainst accidental reactiv

Pagina 33

Initial Sta rt-up and Service39Procedure (continued)2. Cleaning heat exchanger (continued)ServiceService10. Inspect combustion chamber byusing a flash

Pagina 34 - Initial Start-up

Contents4PageSafetyImportant Regulatory and Installation Requirements 7...General InformationAbout these Installation Instructions 8...

Pagina 35

Initial Sta rt-up and Service40Procedure (continued)3. Check flue pipe and vent terminationServiceServiceRepair or replace as necess ary.4. Check pres

Pagina 36 - Service Schedule

Initial Sta rt-up and Service41Procedure (continued)6. Check for proper combustion air supply and ventilation for the boilerServiceService7. Ensure no

Pagina 37 - Initial Sta rt-up and Service

Additional Information42Troubleshooting GuideFan does not start RemedyThermostat not calling for heat Turn up room thermostatNo 120V power Check 120V

Pagina 38 - Service Procedure

Additional Information43Troubleshooting Guide (continued)Fan runs, pilot lights, burner short cycles RemedyThermostat anticipator t oo low Set anticip

Pagina 39 - Procedure (continued)

Additional Information44Technical DataLegendVent connection, Ø 3” / 76 mmBoiler water supply, 1¼” / 32 mm120V power in120V outlet for pump(max. 4 Amp.

Pagina 40

Additional Information45Technical Data (continued)Boiler ModelModelNo.ECV-65 ECV-80 ECV-100 ECV-115 ECV-140 ECV-155 ECV-180 ECV-200CSA input MBHkW6519

Pagina 41

Additional Information46Wiring Diagram - Vitogas 050, ECV with Honeywell Intermittent Pilot200°F120V120V120V5167 450 v1.4

Pagina 42 - Troubleshooting Guide

Additional Information47Ladder Diagram - Vitogas 050, ECV with Honeywell Intermittent Pilot24 VLNVALVEGASS8600(H,M)HONEYWELLM45SEQUENCE OF OPERATION1.

Pagina 43 - Additional Information

Additional Information48Parts ListParts001 Left panel002 Right panel003 Back panel004 Top panel005 Front access panel006 Front upper panel007 Mid pane

Pagina 44 - Technical Data

Additional Information49Parts List (continued)Honeywell12345678910121316171819202122232425272628293031323334353741403942434445464748521415535455564950

Pagina 45 - Technical Data (continued)

Contents (continued)5PageInitial Start-up and ServiceInitial Start-up 34...Al

Pagina 46

Additional Information50Maintenance RecordMaintenance/Service Maintenance/Service Maintenance/Service Maintenance/Service Maintenance/Serviceon:by:Mai

Pagina 47

Additional Information51Lighting and Operating Instructions5167 450 v1.4

Pagina 48 - Parts List

Viessmann Manufacturing Company Inc.750 McMurray R oadWaterloo, Ontario • N2V 2G5 • CanadaTel. (519) 885-6300 • Fax (519) 885-0887www.viessmann.ca • m

Pagina 49 - Parts List (continued)

Safety6Important Regulatory and Installation RequirementsCodesThe installation of this unit shall be inaccordance with local codes or, in theabsence o

Pagina 50 - Maintenance Record

Safety7Important Regulatory and Installation Requirements (continued)For direct-vent appliances, mechanical-vent heating appliances or domestic hot wa

Pagina 51

General Information8About these Installation InstructionsTake note of all symbols and notations intended to draw attention to potential hazards or imp

Pagina 52

General Information9Product InformationThe Vitogas 050, ECV boiler is for use in closed-loop forced circulation hot waterheating systems only. Boiler